Electrical • Mechanical • Technology
East Penn Manufacturing, is battery finish and distribution center. This facility was built on a 40-acre greenfield site. It is a 345,000 SF pre-engineered and conventional steel frame building with pre-cast concrete and insulated metal panel exterior.
It was designed to FM global standards. With 58,000 SY of concrete paving, 24 miles of pipe, over 200 miles of wire, 1,365 control valves, and 3,500 hours of BIM coordination and modeling…it is certainly a project for all involved to be proud of!
Electrical
Mechanical
[sp_wpcarousel id=”1780″]
An intermediate floor was added to the remaining north half of the gymnasium to create two levels. On the upper level, a storage mezzanine was created. Under the storage mezzanine, new, larger locker rooms/restrooms was added. In addition, a reception area, entry vestibule, principal’s office and new classroom were added.
Bluestone Engineering provided complete MEPT/FP design. New, energy efficient LED lighting and lighting controls were specified for the new and renovated areas, plus the parking lots. Rough-in was provided for a permanent and portable theatrical lighting system and sound system for the gymnasium.
The existing fire alarm system was expanded to provide voice annunciation in the new and renovated areas of the building with the capacity to extend to the entire building in the future. A grease interceptor was installed underground outside the building to meet current WRA requirement. New HVAC units were specified for the additions. A fire protection service was installed throughout the new additions and renovated areas, but was designed to eventually serve the entire school.
Square Feet: Demo: 2,200 Remodel: 3,000 Addition: 6,800
Budget: $3,336,000
Architect: BSB Design
General Contractor: Ball Team